Construction – Summer 2026 to Winter 2030

Overview

This schedule is tentative and based on the completion of design and financing. Construction will take place in six phases, with work occurring in 2–3 buildings per phase.

During each phase, residents in the affected buildings will be temporarily relocated for approximately nine months. Residents will receive advance notice and additional information before any relocation occurs.

No one is being asked to move now.
Future meetings will be held to explain the relocation process in detail.

Construction Timeline by Phase

Phase 1 — Fall 2026

Buildings: 1, 2, and 3
Additional scope: New Property Management Office

Phase 2 — Spring 2027

Buildings: 9 and 16

Phase 3 — Winter 2028

Buildings: 11 and 12

Phase 4 — Fall 2028

Buildings: 13, 14, and 15

Phase 5 — Summer 2029

Buildings: 4, 5, and 6

Phase 6 — Spring 2030

Buildings: 7, 8, and 10

Previous
Previous

Design – July 2025 – Summer 2026