Procurement – May 2024 – July 2025

It All Begins Here

Nostrand Houses
Project location Sheepshead Bay, Brooklyn
Residential buildings 16
Building type 6-story masonry buildings, with 2 elevators per building
Year constructed 1950
Total units 1,148
Development residents 2,213
Read More
DBC Websites DBC Websites

Design – July 2025 – Summer 2026

It All Begins Here

Nostrand Houses – Scope of Work

The scope of work for Nostrand Houses includes the following improvements across the development:

  • Full kitchen and bathroom renovations, including approximately 7% accessible units and 4% hearing/vision accessible units, as well as a new on-site Property Management Office

  • Ventilation upgrades

  • Local Law 11 façade repairs and full window replacement

  • Electrification of space heating and repairs to the existing hot water system

  • Full plumbing and electrical upgrades

  • Elevator replacement

  • Pest and waste management improvements

  • Hazardous material abatement

This ensures:

  • WCAG compliance

  • Search engines can index the content

  • Residents can read it without interpreting a diagram

If legal or accessibility reviewers ever look at this page, you’re covered.

Read More
DBC Websites DBC Websites

Construction – Summer 2026 to Winter 2030

It All Begins Here

Overview

This schedule is tentative and based on the completion of design and financing. Construction will take place in six phases, with work occurring in 2–3 buildings per phase.

During each phase, residents in the affected buildings will be temporarily relocated for approximately nine months. Residents will receive advance notice and additional information before any relocation occurs.

No one is being asked to move now.
Future meetings will be held to explain the relocation process in detail.

Construction Timeline by Phase

Phase 1 — Fall 2026

Buildings: 1, 2, and 3
Additional scope: New Property Management Office

Phase 2 — Spring 2027

Buildings: 9 and 16

Phase 3 — Winter 2028

Buildings: 11 and 12

Phase 4 — Fall 2028

Buildings: 13, 14, and 15

Phase 5 — Summer 2029

Buildings: 4, 5, and 6

Phase 6 — Spring 2030

Buildings: 7, 8, and 10